DETAIL PROGRESS KNMP

100
Lokasi Progress Bergerak
32.53%
Progress Nasional
0.31%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Mattiro Bombang SULAWESI SELATAN
+75%
Lasama SULAWESI TENGGARA
+59%
Lakara SULAWESI TENGGARA
+59%
Labone SULAWESI TENGGARA
+58%
Muara Sampara SULAWESI TENGGARA
+58%
Lero Pinrang SULAWESI SELATAN
+54%
Latawe SULAWESI TENGGARA
+53%
Bangko SULAWESI TENGGARA
+53%
Bone Pute SULAWESI SELATAN
+52%
Terapung SULAWESI TENGGARA
+53%
Lumpue SULAWESI SELATAN
+51%
Tamarupa SULAWESI SELATAN
+51%
Bungeng SULAWESI SELATAN
+51%
Bassiang Timur SULAWESI SELATAN
+50%
Borimasunggu SULAWESI SELATAN
+52%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI TENGGARA 15 45.53% 4 11
SULAWESI SELATAN 50 37.68% 7 43
SULAWESI BARAT 6 32.83% 0 6
SULAWESI TENGAH 14 29.50% 2 12
GORONTALO 11 18.00% 1 10
SULAWESI UTARA 8 1.00% 2 6
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI TENGGARA 45.53%
SULAWESI SELATAN 37.68%
SULAWESI BARAT 32.83%
SULAWESI TENGAH 29.50%
GORONTALO 18.00%
SULAWESI UTARA 1.00%
DISTRIBUSI PROGRESS NASIONAL
0%
4
1-25%
26
26-50%
59
51-75%
15
76-99%
0
100%
0
PROGRESS TERBARU
Lakawali Pantai
SULAWESI SELATAN

47% Pekerjaan DPT
Pemasangan mal DPT
2026-10-28 19:54:00
Polewali
SULAWESI TENGGARA

29% Pekerjaan Pengecoran dan Revetment
= pek. Pengecoran lantai kerja Footflat = pek. Revetment
2026-10-28 19:48:00
Takkalala
SULAWESI SELATAN

37% Pekerjaan Pabrik Es Portable
* Pek.pemasangan pondasi pabrik es portable
2026-10-28 19:40:00
Karang-karangan
SULAWESI SELATAN

45% Pekerjaan Tambatan Perahu dan Pabrik Es Portable
* Pekerjaan pemasangan bekisting balok tambatan perahu * Pek.pondasi bangunan pabrik es
2026-10-28 19:36:00
Mekkatta Selatan
SULAWESI BARAT

33% Pekerjaan Revetment dan Saluran
* pek.pasangan batu revetment * pek.pasangan batu saluran
2026-10-28 19:13:00
Tubo Selatan
SULAWESI BARAT

31% Pekerjaan Pengecoran DPT
• Pek.pengecoran dinding DPT
2026-10-28 19:10:00
Pallameang
SULAWESI SELATAN

33% Pek DPT dan Shelter Pendaratan Ikan
* Pek. Pengecoran sloof pada bangunan shelter pendaratan ikan * Pek. Pemasangan bekisting dan pengecoran dinding penahan tanah revetment
2026-10-28 19:10:00
Tubo Poang
SULAWESI BARAT

25% Pekerjaan Pabrik Es Portable
• Pek.perakitan pembesian pabrik es
2026-10-28 19:08:00
Sumpang Binangae
SULAWESI SELATAN

10% Pekerjaan Dinding Penahan Tanah
Galian Pondasi Dinding Penahan Tanah
2026-10-28 19:07:00
Balo-Balo
SULAWESI SELATAN

39% Pekerjaan Pabrik Es Portable
* Pemasangan pondasi batu kosong Pabrik es portable
2026-10-28 19:04:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00146
Malalan
SULAWESI TENGAH PENYANGGA 12% 2026-10-28 09:33:20 Lihat Site
SITE00151
Sumpang Binangae
SULAWESI SELATAN PENYANGGA 10% 2026-10-29 11:08:38 Lihat Site
SITE00132
Taula'a
GORONTALO PENYANGGA 9% 2026-10-26 12:18:47 Lihat Site
SITE00180
Naha 1
SULAWESI UTARA PENYANGGA 3% 2026-11-02 09:34:17 Lihat Site
SITE00145
Lero Donggala
SULAWESI TENGAH PENYANGGA 2% 2026-10-28 09:29:42 Lihat Site
SITE00181
Gangga 2
SULAWESI UTARA PENYANGGA 2% 2026-10-30 13:11:17 Lihat Site
SITE00179
Kahuhu
SULAWESI UTARA PENYANGGA 2% 2026-10-29 13:17:16 Lihat Site
SITE00106
Muara Bone
GORONTALO PENYANGGA 1% 2026-10-08 15:55:53 Lihat Site
SITE00133
Tontayuo
GORONTALO PENYANGGA 1% 2026-10-26 12:18:15 Lihat Site
SITE00182
Lamanggo
SULAWESI UTARA HUB 1% 2026-10-29 13:21:33 Lihat Site