← Kembali ke Peta

DETAIL PROGRESS KNMP

22
Lokasi Progress Bergerak
0.32%
Progress Nasional
0%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Mattiro Bombang SULAWESI SELATAN
+5%
Borimasunggu SULAWESI SELATAN
+1%
Bassiang Timur SULAWESI SELATAN
+1%
Bone Pute SULAWESI SELATAN
+1%
Belopa SULAWESI SELATAN
+1%
Karang-karangan SULAWESI SELATAN
+1%
Tirowali SULAWESI SELATAN
+1%
Lero SULAWESI SELATAN
+1%
Pallameang SULAWESI SELATAN
+1%
Padang Kalua SULAWESI SELATAN
+0%
Bababulo SULAWESI BARAT
+0%
Lumpue SULAWESI SELATAN
+0%
Binanga Karaeng SULAWESI SELATAN
+0%
Takkalala SULAWESI SELATAN
+0%
Limbua SULAWESI BARAT
+0%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI SELATAN 50 0.66% 7 43
SULAWESI BARAT 6 0.33% 0 6
GORONTALO 21 0.00% 2 19
SULAWESI TENGGARA 17 0.00% 4 13
SULAWESI TENGAH 14 0.00% 2 12
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI SELATAN 0.66%
SULAWESI BARAT 0.33%
GORONTALO 0.00%
SULAWESI TENGGARA 0.00%
SULAWESI TENGAH 0.00%
DISTRIBUSI PROGRESS NASIONAL
0%
86
1-25%
22
26-50%
0
51-75%
0
76-99%
0
100%
0
PROGRESS TERBARU
Bassiang Timur
SULAWESI SELATAN

2% Leveling Lahan dan Sondir
Pekerjaan Leveling Lahan dan Sondir
2026-08-03 11:08:00
Padang Kalua
SULAWESI SELATAN

1% Mobilisasi Materials
Mobilisasi Materials
2026-08-03 11:06:00
Tirowali
SULAWESI SELATAN

2% Pemagaran
Pekerjaan pemagaran lokasi proyek
2026-08-03 11:04:00
Bone Pute
SULAWESI SELATAN

2% Lanjutan Leveling Lahan
Pekerjaan Penimbunan
2026-08-03 11:00:00
Bulete
SULAWESI SELATAN

1% Mobilisasi Materials
Mobilisasi Materials
2026-08-03 10:55:00
Karang-karangan
SULAWESI SELATAN

2% Pekerjaan Pembesian
Pekerjaan Pembesian
2026-08-03 10:47:00
Borimasunggu
SULAWESI SELATAN

2% Cleaning & Pemagaran
* Pembersihan Area Kerja * Pemasangan Pagar Sementara * Galian Dinding Penahan Tanah
2026-08-01 10:26:00
Belopa
SULAWESI SELATAN

2% Pekerjaan Sondir
Pekerjaan Sondir
2026-07-31 10:35:00
Tirowali
SULAWESI SELATAN

1% Pekerjaan Penimbunan, Penerimaan Kayu Dolken, dan Pengukuran
Pekerjaan Penimbunan Tanah, Penerimaan Kayu Dolken, dan pengambilan Topografi untuk mengetahui volume timbunan
2026-07-29 10:50:00
Tamarupa
SULAWESI SELATAN

1% Persiapan Awal
* Pembuatan Bedeng Pekerja Dan Gudang * Pengirim Material Tanah Urug * Land Clearing
2026-07-29 09:18:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00081
Mattiro Bombang
SULAWESI SELATAN PENYANGGA 6% 2026-07-27 09:49:05 Lihat Site
SITE00099
Pallameang
SULAWESI SELATAN PENYANGGA 2% 2026-07-28 12:17:09 Lihat Site
SITE00096
Lero
SULAWESI SELATAN HUB 2% 2026-07-31 14:17:05 Lihat Site
SITE00078
Borimasunggu
SULAWESI SELATAN PENYANGGA 2% 2026-08-03 10:29:30 Lihat Site
SITE00033
Bone Pute
SULAWESI SELATAN PENYANGGA 2% 2026-08-03 11:01:51 Lihat Site
SITE00030
Belopa
SULAWESI SELATAN HUB 2% 2026-08-03 10:36:14 Lihat Site
SITE00029
Bassiang Timur
SULAWESI SELATAN PENYANGGA 2% 2026-08-03 11:09:32 Lihat Site
SITE00025
Tirowali
SULAWESI SELATAN HUB 2% 2026-08-03 11:05:11 Lihat Site
SITE00023
Karang-karangan
SULAWESI SELATAN PENYANGGA 2% 2026-08-03 10:49:14 Lihat Site
SITE00160
Tadang Palie
SULAWESI SELATAN PENYANGGA 1% 2026-08-03 08:42:42 Lihat Site