← Kembali ke Peta

DETAIL PROGRESS KNMP

100
Lokasi Progress Bergerak
32.53%
Progress Nasional
0.31%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Mattiro Bombang SULAWESI SELATAN
+75%
Lakara SULAWESI TENGGARA
+59%
Lasama SULAWESI TENGGARA
+59%
Labone SULAWESI TENGGARA
+58%
Muara Sampara SULAWESI TENGGARA
+58%
Lero Pinrang SULAWESI SELATAN
+54%
Bangko SULAWESI TENGGARA
+53%
Latawe SULAWESI TENGGARA
+53%
Bone Pute SULAWESI SELATAN
+52%
Terapung SULAWESI TENGGARA
+53%
Bungeng SULAWESI SELATAN
+51%
Lumpue SULAWESI SELATAN
+51%
Tamarupa SULAWESI SELATAN
+51%
Tondasi SULAWESI TENGGARA
+50%
Takkalasi SULAWESI SELATAN
+51%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI TENGGARA 15 45.53% 4 11
SULAWESI SELATAN 50 37.68% 7 43
SULAWESI BARAT 6 32.83% 0 6
SULAWESI TENGAH 14 29.50% 2 12
GORONTALO 11 18.00% 1 10
SULAWESI UTARA 8 1.00% 2 6
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI TENGGARA 45.53%
SULAWESI SELATAN 37.68%
SULAWESI BARAT 32.83%
SULAWESI TENGAH 29.50%
GORONTALO 18.00%
SULAWESI UTARA 1.00%
DISTRIBUSI PROGRESS NASIONAL
0%
4
1-25%
26
26-50%
59
51-75%
15
76-99%
0
100%
0
PROGRESS TERBARU
Lero Pinrang
SULAWESI SELATAN

43% Pekerjaan Tambatan Perahu, Saluran, Bangunan Genset, Kantor Pengelola dan Revetment
* Pek. Pembesian besi ringbalk pemasangan bekisting ringbalk dan pengecoran ringbalk/RB-1 pada tambatan perahu * Pek. Perakitan dan pemasangan bekisting ringbalk bangunan docking kapal * Pek. Saluran drainase pemasangan batu bela * Pek. Pasangan bata merah pada bangunan genset * Pek.Bangunan kantor pengelola * Pek. Plesteran tangga revetment * Fabrikasi pembesian
2026-10-09 22:35:00
Tanjung Laimeo
SULAWESI TENGGARA

39% Pekerjaan Tambatan Perahu
= pek. Tambatan perahu
2026-10-08 20:38:00
Lumpue
SULAWESI SELATAN

35% Pekerjaan DPT, Revetment dan Pembesian
* Pek. Pengecoran dinding penahan tanah * Pek. Tangga revetment pasangan batu * Pek. Pembesian besi pondasi tapak * Fabrikasi pembesian
2026-10-08 20:24:00
Watang soreang
SULAWESI SELATAN

8% Pekerjaan Saluran dan DPT
* Pek. Plesteran saluran * Pek. Pembesian dinding penahan tanah * Fabrikasi pembesian
2026-10-08 20:22:00
Mekkatta Selatan
SULAWESI BARAT

25% Pekerjaan Revetment dan DPT
* pek.pondasi * pek.galian revetmen * pek.pemasangan cerucuk dolken * pek.bekisting DPT
2026-10-08 20:19:00
Padang Kalua
SULAWESI SELATAN

28% Pekerjaan Tambatan Perahu
•pemasangan bekisting kolom tambatan perahu
2026-10-08 19:41:00
Karang-karangan
SULAWESI SELATAN

36% Pekerjaan Revetment
Pek. Pabrikasi pembesian revetment
2026-10-08 19:39:00
Ulu Sawa
SULAWESI TENGGARA

35% Pekerjaan Kios Perbekalan, Shelter Pendaratan Ikan dan Tambatan Perahu
= pek. Kios pembekalan = pek. Selter pendaratan ikan = pek. Tambatan perahu
2026-10-08 19:35:00
Burau Pantai
SULAWESI SELATAN

37% Pekerjaan Pabrik Es dan DPT
- Pek. Pondasi pabrik es - Pengecoran dpt
2026-10-08 18:32:00
Muara Bone
GORONTALO

1% Pekerjaan Persiapan

2026-10-08 15:54:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00081
Mattiro Bombang
SULAWESI SELATAN PENYANGGA 75% 2026-10-27 09:25:43 Lihat Site
SITE00026
Lasama
SULAWESI TENGGARA PENYANGGA 59% 2026-11-02 09:26:29 Lihat Site
SITE00057
Lakara
SULAWESI TENGGARA PENYANGGA 59% 2026-10-28 09:41:17 Lihat Site
SITE00042
Labone
SULAWESI TENGGARA PENYANGGA 58% 2026-11-02 10:10:45 Lihat Site
SITE00138
Muara Sampara
SULAWESI TENGGARA PENYANGGA 58% 2026-10-30 09:57:30 Lihat Site
SITE00096
Lero Pinrang
SULAWESI SELATAN HUB 54% 2026-11-02 09:43:45 Lihat Site
SITE00143
Bangko
SULAWESI TENGGARA HUB 53% 2026-10-30 15:14:05 Lihat Site
SITE00034
Latawe
SULAWESI TENGGARA PENYANGGA 53% 2026-11-02 09:31:54 Lihat Site
SITE00134
Terapung
SULAWESI TENGGARA HUB 53% 2026-11-02 09:53:12 Lihat Site
SITE00078
Borimasunggu
SULAWESI SELATAN PENYANGGA 52% 2026-10-26 14:44:43 Lihat Site