DETAIL PROGRESS KNMP

100
Lokasi Progress Bergerak
33.20%
Progress Nasional
0.32%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Mattiro Bombang SULAWESI SELATAN
+75%
Lakara SULAWESI TENGGARA
+59%
Lasama SULAWESI TENGGARA
+59%
Labone SULAWESI TENGGARA
+58%
Muara Sampara SULAWESI TENGGARA
+58%
Lero Pinrang SULAWESI SELATAN
+54%
Bangko SULAWESI TENGGARA
+53%
Latawe SULAWESI TENGGARA
+53%
Bone Pute SULAWESI SELATAN
+52%
Terapung SULAWESI TENGGARA
+53%
Lumpue SULAWESI SELATAN
+52%
Limbua SULAWESI BARAT
+52%
Bungeng SULAWESI SELATAN
+51%
Podi SULAWESI TENGAH
+51%
Tamarupa SULAWESI SELATAN
+51%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI TENGGARA 15 45.53% 4 11
SULAWESI SELATAN 50 38.22% 7 43
SULAWESI BARAT 6 38.17% 0 6
SULAWESI TENGAH 14 30.29% 2 12
GORONTALO 11 18.00% 1 10
SULAWESI UTARA 8 1.00% 2 6
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI TENGGARA 45.53%
SULAWESI SELATAN 38.22%
SULAWESI BARAT 38.17%
SULAWESI TENGAH 30.29%
GORONTALO 18.00%
SULAWESI UTARA 1.00%
DISTRIBUSI PROGRESS NASIONAL
0%
4
1-25%
24
26-50%
59
51-75%
17
76-99%
0
100%
0
PROGRESS TERBARU
Songka
SULAWESI SELATAN

24% Pekerjaan DPT
Pekerjaan pondasi tapak DPT
2026-10-02 19:57:00
Ponjalae
SULAWESI SELATAN

25% Pekerjaan Precast
pemasangan precast
2026-10-02 19:55:00
Sienjo
SULAWESI TENGAH

25% Pekerjaan Precast dan Saluran
- bekesting batako -Acian drainase
2026-10-02 19:41:00
Pasi-Pasi
SULAWESI SELATAN

24% Pekerjaan Pondasi dan Cerucuk Dolken
* Pemasangan dolken * Galian pondasi * Mobilisasi material
2026-10-02 19:36:00
Ulu Sawa
SULAWESI TENGGARA

33% Pekerjaan Tambatan Perahu
= pek. Tambatan perahu = pek. Ring balok tambatan Perahu = pek. Pabrik es dan ipal
2026-10-02 19:01:00
Kupa
SULAWESI SELATAN

22% Pekerjaan Pembesian
* Fabrikasi Pembesian Foot Plate
2026-10-02 16:43:00
Watolo
SULAWESI TENGGARA

31% Pekerjaan Tambatan Perahu

2026-10-02 16:40:00
Rata
SULAWESI TENGAH

33% Pekerjaan Pondasi, Levelling Tanah dan Precast
Pekerjaan Pondasi Levelling Lahan Pekerjaan Precast
2026-10-02 15:47:00
Tanjung Bunga
SULAWESI TENGGARA

26% Pekerjaan DPT
= pek. Dinding penahan tanah
2026-10-02 09:44:00
Tasiwalie
SULAWESI SELATAN

21% Pekerjaan DPT dan Revetment
* Pek. Tangga revetment pasangan batu kosong * Pek. Cerucuk dolken * Pek. Bekisting dinding penahan tanah
2026-10-01 20:15:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00020
Songka
SULAWESI SELATAN PENYANGGA 24% 2026-10-26 11:14:24 Lihat Site
SITE00152
Darubiah
SULAWESI SELATAN PENYANGGA 23% 2026-10-28 10:24:05 Lihat Site
SITE00139
Muara Tinobu
SULAWESI TENGGARA PENYANGGA 21% 2026-11-02 10:12:33 Lihat Site
SITE00087
Watang soreang
SULAWESI SELATAN PENYANGGA 21% 2026-11-03 09:31:16 Lihat Site
SITE00150
Siddo
SULAWESI SELATAN PENYANGGA 21% 2026-10-29 11:07:18 Lihat Site
SITE00111
Olimoo'O
GORONTALO PENYANGGA 15% 2026-10-20 11:58:48 Lihat Site
SITE00114
Biluhu Tengah
GORONTALO PENYANGGA 15% 2026-10-20 11:59:38 Lihat Site
SITE00131
Olimeyala
GORONTALO PENYANGGA 15% 2026-10-26 12:19:33 Lihat Site
SITE00085
Moilong
SULAWESI TENGAH PENYANGGA 14% 2026-10-21 09:41:32 Lihat Site
SITE00146
Malalan
SULAWESI TENGAH PENYANGGA 12% 2026-10-28 09:33:20 Lihat Site